InvestigationAugust 27, 2026
Alaska's $184M Port MacKenzie rail extension: 25 of 32 miles built, no trains yet
Promised a Fall 2015 ribbon cutting for a 32-mile freight rail link to Port MacKenzie, the project has absorbed $184 million in state funding — with track, ties, ballast and signals still missing from most of the line.
Source award
Alaska Railroad Corp / Matanuska-Susitna Borough — $184,000,000 from AK-LEG-CAPEX, FY2026.
Sources (2)
- https://www.alaskarailroad.com/sites/default/files/akrr_pdfs/2012_01_17_Port_Mac_Display_Boards_PROJ.pdf
“Final design underway for 32-mile preferred route corridor from the port to the mainline at Houston... Ribbon Cutting Fall 2015”
- https://citizenportal.ai/articles/6306837/Rail-extensions-to-Port-MacKenzie-and-north-face-large-funding-gaps-railroad-seeks-partners-and-grants
“$184 million already contributed by the State of Alaska... cost to complete the rail line is $300 million”