Rail Funding Recipient

Southwest Pennsylvania Railroad Co.

Summary

Total awarded, on record
$8,400,000
Confirmed awards
4
Award years
FY2017–FY2025
Programs won
1

Award History

  • PA-COMBINED$3,240,000 · FY2025

    rehabilitate 3 miles of rail replacing jointed rail on the Radebaugh Subdivision with welded rail

    Source →
  • PA-COMBINED$1,860,000 · FY2024

    rehabilitate 2.5 miles of rail replacing jointed rail on the Radebaugh Subdivision with welded rail

    Source →
  • PA-COMBINED$1,500,000 · FY2018

    rehabilitate and improve approximately 2.6 miles of track on the FM&P Subdivision by installing continuous welded rail and realigning and surfacing track

    Source →
  • PA-COMBINED$1,800,000 · FY2017

    replace and surface three miles of track with continuous welded rail from Broadford to the Fayette County line to improve safety and operations

    Source →

Methodology

This page shows confirmed awards only, each linked to its original source. Amounts reflect the award ceiling reported at the time of selection and are not always the final obligated amount. Unsuccessful applications are not public record, so this page makes no win-rate or odds claim — it shows what this organization has won, not what it applied for.